Financials

Remuera New Build (5BR) · BC JOB-0244 · Percentage of Completion

All BC-owned rolls (Job total budget, Job Task usage, contract totals) come from BcJobView + BcJobTaskView. Bode-Postgres contributes only the change-order delta.

BC budget cost

$2,200,000

Sum of Budget Job Planning Lines

Contract value

$2,640,000

Sum of Billable Job Planning Lines

Adjusted contract

$2,640,000

no approved COs

Gross margin

$440,000

16.7%

Spend progress

$256,400 / $2,200,000

11.7% of BC budget cost consumed (Job Task usage)

Change orders

Approved (in BC)
$0
Pending
$0
Invoiced
$310,000
Outstanding to invoice
$2,330,000
Manage change orders →

Per Job Task — budget vs. usage (from BC)

Task #DescriptionBudgetContractUsageVariance
1000Demolition & site prep$38,000$46,000$38,400+1.1%
1100Foundations$220,000$264,000$218,000-0.9%
1200Framing — multiple stages$410,000$492,000$0-100.0%
1300Cladding & roofing$320,000$384,000$0-100.0%
1400Services rough-in$280,000$336,000$0-100.0%
1500Interior fitout$720,000$864,000$0-100.0%
1600Landscape & external works$132,000$158,000$0-100.0%
1700CCC & handover$80,000$96,000$0-100.0%
9999Total$2,200,000$2,640,000$256,400