Change orders
Kingsland Villa Renovation · 3 change orders · approved impact -$2,150
CO-001Upgrade kitchen splashback to ceramic tile
Client reviewClient requested a tiled splashback rather than the painted finish in the original spec. Affects the fitout phase only.
$3,850
+1d schedule
CO-002Additional double-glazing — north elevation
PricingLate spec change for thermal performance. Triggers a re-order of joinery and a 2-day delay to exterior cladding.
$12,400
+2d schedule
CO-003Remove planned skylight in master bath
ApprovedClient opted out post-framing. Saves cost; no schedule impact because framing already accommodated.
-$2,150
no schedule impact